A Critical Review of Project Management- The need of the hour

1.Introduction:

Successful project management has several significant characteristics. To the value of project management, it is necessary to understand the fundamental nature of a project; the core characteristics of project management processes; how success is evaluated, the roles, responsibilities, and activities of a project manager and the expertise required; and the context in which projects are performed. Orissa tribal development project started in December 1987 with the total budget cost about USD 24.4 million. The main aim of this project is to help the tribal peoples and improve their status in the society by a sustainable economic uplift. The beneficiaries consisted of some 12 500 tribal families and another 4 000 local non-tribal households.

2. Project design and objectives

The OTDP[1] was approved by IFAD’s Executive Board in December 1987. The total project cost was USD 24.4 million, out of which IFAD’s loan at a highly concessional rate was equal to USD 12.2 million. The project was co-financed by the WFP in the form of a grant of USD 1.4 million, and the balance was made up of domestic contributions. IFAD’s co-operating institution for the project was the United Nations Office for Project Services (UNOPS), and the executing agency was the Harijan and Tribal Welfare Department of the GOO. At project closure, 84% of IFAD’s loan was disbursed, although by 8 June 1998 all remaining funds had also been disbursed.

3. Objectives and components

The project was to achieve its objectives through an integrated programme of investments in agriculture production and natural resource development (for which 42% percent of the loan was reserved), human resource development (6.5%), rural infrastructure (10%), land survey and settlement (5.5%), and implementation management support (8 %). In addition to these components accounting for 72% of IFAD’s loan (base costs), a physical contingency of 2% and price contingency of 26% were included.

4. Evaluation:

4.1 Project implementation performance

Good achievements were made in the infrastructure development component, and appraisal targets were even exceeded in some cases, e.g., 130 kms of rural roads were upgraded/constructed (as against the 120 kms envisaged), which now provide a vital lifeline for transport and communications in an area where access to remote villages/tribal areas previously was very treacherous. Another interesting aspect related to infrastructure development was the wage employment generated during the project – the tribals were provided both with food-for-work and a token salary in return for their labour in developing project-related infrastructure. However, once infrastructure activities were completed, employment opportunities were absent, thus leaving the tribals without the cash-in-hand they had received through OTDP. Another area where the project was relatively successful was in land surveying and settlement activities. In fact, the project played an instrumental role in land surveying and distribution to tribal families. During the implementation period, in 236 villages a record of rights for dongar (hills) land was issued to 6 837 tribal beneficiaries (in the names of both husband and wife) covering a total area of 17 175 acres. This has added significantly to the social and economic securities of the tribals. However, the aspect that still requires further clarification is the conservation and management of common property resources, which are a significant source of livelihood for the tribals.

The project also made some achievements through the agriculture and natural resources development component. The project introduced the replacement of traditional and low-yield varieties of seeds by high-yielding hybrid varieties, and constructed 221 water harvesting structures for irrigation. However, some areas which did not fare well include the construction of diversion dams, and vegetative bunding, which has been done only on 50% of the land targeted. In an all the area which caused impediments to implementation was project management. First and foremost was the frequent change in project managers. The OTDP had in all twelve project managers in an implementation period spanning nine years, which obviously prevented a minimum degree of continuity.

 

4.2 Project disbursement and supervision

At the time of the project’s original closing date (31 March 1996), 51 percent of IFAD’s loan had been disbursed. However, upon the recommendation of UNOPS and the request of GOI, IFAD extended the project till end-1997 to enable full disbursement of its loan and an appropriate completion of the works. UNOPS as the cooperating institution was responsible for: (i) supervising the project; and (ii) administering the loan. However, there are some areas which would have required greater UNOPS follow-up. For instance, despite the fact that nearly all aide-memoires of supervision missions repeatedly expressed the need for improving the reporting, auditing and M&E functions of the project, such problems were not adequately taken-up in the supervision reports which followed, nor was IFAD’s attention sufficiently drawn to these matters. The project would have benefited from the occasional participation in supervisions of selected technical experts, such as in agriculture, irrigation, training, M&E and project management.

 

4.3 Analysis, impact and sustainability

State government officials prepared the plans for tribal development, in which some central government officials also took part. IFAD on its side provided a broad format for project development, but the process of formulation did not bring in innovative approaches and measures. The approach to tribal development embedded in the project had lacunae. It was essentially a techno-economic intervention. Its principal concerns were raising agricultural productivity and building rural infrastructure, especially roads. From an agricultural point of view, the allocation of parcels of lands and the provision of land titles has reduced shifting cultivation practices in the areas targeted, having a positive impact on the agricultural and natural resource base of the block. However, as far as the the practice of community ownership over forestlands is concerned the project did not address satisfactorily.

]]>

The participation of tribals in the HRD programmes was low. The guidelines suggested for the involvement of a reputed NGO to implement the HRD programme, including educational and skill development programmes, as well as training to build awareness on issues such as environmental concerns, social conditions, trading practices, and legal and land rights. The quality of training imparted under the project was questionable. The contents of the training programmes did not cover many important areas, such as environment concerns, social reforms, exploitation in trading, money lending and women’s rights. The extreme importance of integrating education and health programmes in the context of agriculture and rural development activities was also not addressed by the OTDP.

The issue of sustainability is of major importance, and the upkeep of most project-initiated activities is of concern. For instance, with regard to the physical infrastructure developed under the project, the irrigation systems and rural roads were found to be deteriorating at the time of the evaluation mission. Wage-employment impacted the lives of the tribal since it provided a means to supplement their income during implementation. In terms of proportion, OTDP figures illustrate that of the total additional employment created, seventy-five percent of the employment was provided to male labourers. What was distressing is that a high proportion (twenty-five percent of the total sample in the project area) of households engaged their children in such activities. Female labourers were mainly employed on their own land and in the collection of non-wood forest produce, whereas males tended to work as casual wage-employment outside. . In sum, the project created opportunities for employment, but these ceased after project closure. At that time, the tribal were left without the remuneration they had received through OTDP. Having got used to cash-in-hand, the tribal have been forced to revert to moneylenders, which has once again aggravated their indebtedness problem.

 

5. Lessons learned:

5.1 Human resources development

The project did not recognise the prime importance and contribution of the HRD component to the entire project process. This component, which represented the “software side” of development activities such as building participation, training and education, was a crucial input for the ultimate success and impact of the project. Unfortunately, project designers only allocated around six percent of total project costs to this component. Right from design the project had over-bearing faith in technology, and attached great importance to establishing the hardware (physical infrastructure, agriculture development, land allocation, etc.) for the development process. What the OTDP experience has highlighted is the need to “prepare” the development process by concrete efforts firstly in social development and social mobilisation, prior to launching the full-blown productive investment activities. In this way the target group would be sensitised to the project and be in a position to benefit from, and contribute more meaningfully to, project activities.

5.2 Knowledge of the Rural People

The OTDP points to the crucial importance to the development process of the knowledge of the tribal people, be it with regard to agricultural practices, land and water management, agro and food-processing, medicinal matters, environmental issues or about prevailing culture and ethos. Their know-how has been developed and refined over centuries, which has been transmitted through generations of people. Their knowledge and experiences need to be tapped systematically and blended accordingly with modern practices suitable to the context and environment in which the tribal people live and operate. In such a way, development activities and interventions at large will be more ‘implementable’ and acceptable. Moreover, in this way the chances of impact and sustainability are also higher and there will be ownership in the activities promoted, given that they build upon the tribal peoples know-how and preferences.

5.3 Monitoring and evaluation

M&E is a crucial tool for management and implementation purpose, Selection of indicators for the monitoring system should be done at latest by project start-up in a consultative process, involving the various stakeholders including the beneficiaries. These should be simple and easily quantifiable to enable data collection at periodic intervals during implementation. If necessary, the indicators should be adjusted according to the evolving priorities of the project, thus highlighting the dynamic nature of monitoring systems. These systems should not be viewed as data gathering instruments, but as tools that play a more important role in informing project management of the status of implementation and exposing the various issues that need adjustments. Evaluation could be outsourced to the private sector, research centres or universities to enable an impartial self-evaluation process. Finally, the contribution of beneficiaries should be sought in the M&E process.

5.4 Participatory approach to design and implementation

The degree of beneficiary participation at all stages in OTDP was limited and this was a contributing factor to the mixed results obtained by the project. Tribal people were seldom involved in developing the annual programme of work and budget, and the project lacked consultation with the targeted population. This created an atmosphere of discontent and lack of confidence towards the implementing authorities. Community and people’s participation is of utmost importance, not only during implementation for the prioritisation of activities to undertake, but should commence right from the design stages to assess the perceptions and requirements of the tribal people. As this process will involve the beneficiaries thoroughly, they are more likely to take responsibility and ownership for their own development process, and thus be committed to the activities being implemented. Further, in order to ensure that project executing authorities and other stakeholders are fully sensitised and in agreement with fostering a participatory approach, intense efforts may be required to create awareness amongst the concerned people through systematic training in the needs and benefits of participatory development.

5.5 Project management

In those projects where special units are created for implementation, like in the OTDP, the role of the Project Manager (PM) is important. PMs are an essential element in ensuring a successful intervention, and the effectiveness of implementation is enhanced when managers and other staff appointments are based on merit and undertaken in a transparent manner. Additionally, continuity for a period of 3-5 years in project management is necessary to build relationships and co-operation among all project stakeholders. PMs should be given appropriate incentives to perform and remain committed to the job. Nevertheless, project designers should also explore alternative and innovative approaches to project management, for example, implementation could be conducted through the private sector or through other institutes or bodies which are not under the command of government structures. The involvement of carefully selected NGOs in project management may also be considered.

5.6 Role of the Co-operating institution

Project supervision should increasingly become a problem-solving exercise rather than a mere periodical inspection. It should be considered as an integral part of the project implementation process. In this regard, experience sharing with project execution personnel and local experts, as well as training through the organisation of workshops/seminars during or at the end of supervision missions should be pursued. In multi-dimension projects like the OTDP, it is important to include specialists on supervision missions with expertise in subject matters related to the project, as and when appropriate. Co-operating Institutions should take advantage of local expertise, not only to save costs, but to ensure adequate input of domestic experience. This will facilitate the understanding of the local context, and improve communication with project beneficiaries and local officers. Finally, the need to lay emphasis on following-up on the recommendations made during previous supervision missions is of utmost importance to project success.

5.7 Role of NGOs

The selection of NGOs must be made with utmost care, taking into account the NGO’s reputation and capability, but also their relationship with all the stakeholders. It is imperative to clearly define in advance the objectives, role and responsibility of the NGO and each partner in the process. To this end, it may even be advisable to identify during project design the NGO to involve, and to make them participate in the design process. In this way, it will be relatively easier to have a common understanding right from the start about what is expected of each partner. At start-up, special team building sessions could be organised to inject a spirit of co-operation and effective participation. This would also be an opportunity for all concerned to appreciate their role and boundaries, as well as to recognise those of the other stakeholders. The project management and the governments on their part should avoid adopting paternalistic and top-down attitudes, and consider the NGO as an equal partner establishing a relationship based on consultation and dialogue.

5.8 Socio-cultural and political sensitivity

Tribal development project and programme need to be designed with due attention to the socio-cultural and political context, if they are to realise their intended objectives and attention should also be given to the caste, class and ethnic origins of the targeted people. This will equip designers with better information of the context in which to develop the intervention and introduce safeguards to ensure that the existing local power structures do not turn out to be the main beneficiaries of tribal development projects and programmes.

5.9 Sustainability

Without the adequate participation in the design, decision-making and implementation of the beneficiaries and their community organisations, the post-project sustainability can be of major concern. This process leads to the much-needed sense of responsibility and ownership of the beneficiaries towards the project, and consequently willingness on their part to maintain project activities. The role of the government is also of importance, not only in terms of their commitment, but also by providing for appropriate institutional support and enabling policy framework. Equally important is the issue of financial sustainability. Governments need to allocate funds to sustain selected project activities after the closing date, and to this end they should introduce a budget line in their core programme budget for the purpose. However, to minimise reliance on counterpart funds for post-project activities, projects should be designed as far as possible in a way to ensure that most of the project activities could be financed without continuous allocation of public resources.

6. Reference:
International Fund for Agriculture Development, Link: http://www.enrap.org.in/Completed.asp?linkid=45
http://operations.ifad.org/web/ifad/operations/country/project/tags/india/214/project overview
Orissa Diary, Link: http://www.orissadiary.com/orissa_profile/tribal/index.asp
India Profile, The Tribes of Orissa, Link: http://www.indiaprofile.com/lifestyle/orissa-tribes.htm
The Focus: ‘Indigenous’India 21, Link: http://www.iias.nl/files/IIAS_NL53_2021.pdf

 

[1] Orissa Tribal Development Project

 Pic  Title  Details
Financial Management for Development (INTRAC NGO Management & Policy) Price:
Avg Review: ( total)
 
All-star advice 2010: our favorite financial experts share their best tips on real estate, investing, taxes, insurance, and debt management--in their ... FINANCE): An article from: Black Enterprise Price: $9.95
Avg Review: ( total)
 
Year-end financial checkup: use this guide to help you evaluate your financial health.(PERSONAL FINANCE): An article from: Black Enterprise Price: $9.95
Avg Review: ( total)
 
Practical Financial Management for NGOs Price:
Avg Review: ( total)
 
Corporate Social Responsibility: Readings and Cases in a Global Context Price: $26.39 - $54.04
Avg Review: ( total)
 
Building Capacity Through Financial Management: A Practical Guide (Oxfam Skills and Practice Series) Price: $3.04 - $14.99
Avg Review: ( total)
 
 View all items... (Powered by: WP Amazon Ads)  

Related Articles:
  • Profile of the UHNWI Philanthropist
  • Financial Planning Services: Get Healthy Present and Wealthy Future
  • Church Financial Software – How to Look for One?
  • A Balanced Strategy: Reprogramming NGOs and Enhancing Their Relevance as Development Partners in Sierra Leone
  • SWOT analysis and challenge of Nile Basin Initiative; an Integrated Water Resource Management perspective